The Water Treatment project is moving quickly. The 2.5 million gallon tank has been completed, tested for leaks (and passed), and is currently being backfilled. We are well underway on the Disinfection Building with the masonry and steel complete. Slabs have been poured and masonry is rising on the Maintenance building. Backwash tank is being finished up and the Arsenic Treatment component is well underway. All wells have been dug with the first much needed CATS well scheduled to be operational several months early in September. Along with the tank work, we have completed about 5 miles of infrastructure improvements to the new facility including sewer and water lines and new pavement.